2017.9.1每日一题:
A senior manager responsible for business transaction identified a system requirement to control the trading risks. The senior manager drafts document required to demonstrate rationality and establish boundaries for the project. A senior manager asks the project manager to starts project planning immediately. What should the project manager do first?
A. Identify stakeholders.
B. Develop project charter
C. Define the project scope.
D. Write a business case.
负责商业交易的高级经理识别到控制交易风险的某个系统需求。高级经理起草了一份包含论证项目合理性与确定项目边界的文件,高级经理要求项目经理立即开始项目规划。项目经理首先应该怎么做?
A、识别干系人
B、制定项目章程
C.、定义项目范围
D、编写商业论证
解析:B。题干中的关键信息“论证项目合理性和确定项目边界”可知,这是制定项目章程的输入之一——商业论证中的内容,参阅PMBOK·P69有原文字。