南湖路k0+1020-k0+1200白灰二次拌和。
![](https://img.haomeiwen.com/i13260192/2562c75cbfd5c749.jpg)
成品。
![](https://img.haomeiwen.com/i13260192/7a32ad83f5d07094.jpg)
地磅基坑制模板。此次地磅基坑挖掘时出现了问题,地磅基坑挖掘比预期大,模板窄于基坑,此时浇筑等混凝土浇至地面时,用土埋住,再浇筑至标高。埋土是防止混凝土从侧面漏出。
![](https://img.haomeiwen.com/i13260192/0a1a7f3a67d8389b.jpg)
小树林荫。
![](https://img.haomeiwen.com/i13260192/4b8748efd16c922d.jpg)
混凝土浇筑现场。
![](https://img.haomeiwen.com/i13260192/0a68994a8224449a.jpg)
震导棒震导过后冒出的气泡。
![](https://img.haomeiwen.com/i13260192/beac3c14afc99314.jpg)
正在浇筑。
![](https://img.haomeiwen.com/i13260192/2d44f833d90f6d72.jpg)
震导棒。
![](https://img.haomeiwen.com/i13260192/b92f74008d211770.jpg)
人工平面。
![](https://img.haomeiwen.com/i13260192/054deb02f135b8e8.jpg)
![](https://img.haomeiwen.com/i13260192/3c05d1ed5037eda1.jpg)
垃圾坑回填处理。
![](https://img.haomeiwen.com/i13260192/2649d946128fd9a7.jpg)
压实。
![](https://img.haomeiwen.com/i13260192/dc486a3082209dfd.jpg)
垃圾坑配置水泥灰,一立方四十kg。
![](https://img.haomeiwen.com/i13260192/a8ad3e8810166c9b.jpg)
![](https://img.haomeiwen.com/i13260192/c9190f8a2a2ebe7e.jpg)
晨曦。
![](https://img.haomeiwen.com/i13260192/a86398d9ceed11b3.jpg)
![](https://img.haomeiwen.com/i13260192/760683bdbc0dec42.jpg)
地磅坑混凝土浇筑。底部标高不一致没关系,只要混凝土厚度达标,顶面标高必须要求一致,保持水平。所以模板安装过程中,各个模板是否保持水平一致很重要。
今日问题
混凝土应该分层浇筑,按照震导棒有效深度分层。
震导棒应该根据自身有效震导半径,一次间隔多少公分进行震导。
尽量避开高温浇筑,混凝土水分丧失太快。
震导棒应该至少两条使用,一条备用。