A new mobile application is in the integration testing phase. To maintain competitive
advantage in an aggressive market, the product manager requests the inclusion of a new feature.
The project manager disagrees with this. What should the project manager do?
A. Immediately implement the new feature to minimize schedule impact.
B. Refuse to implement the feature to minimize time-to-market impact.
C. Prepare and submit a change request to the change control board (CCB).
D. Review the request and obtain project sponsor approval.
一个新的移动应用程序正处于集成测试阶段。为了在激进的市场中保持竞争优势,产品
经理要求包含一项新功能。项目经理不同意。项目经理应该怎么做?
A.立即实施新功能,尽可能减少进度影响。
B.拒绝实施该功能,尽可能减少对投入市场时间的影响。
C.准备并向变更控制委员会(CCB)提交一份变更请求。
D.审查请求并获得项目发起人的批准。
答案:C
解析:无论项目经理自身是否同意变更,都需要通过正式的变更控制流程来处理,范围基
准变更通常由CCB来决定,项目经理通常是CCB的成员之一。