    A project management technique that is currently in widespread use is the () . The
    purpose of this technique is to detail, in hierarchical fashion, all of the activities
    that are required to meet project objectives.
    目前被广泛使用的一种项目管理技术就是工作分解结构( Work Breakdown Structure),其
    目的是采用层次结构的方式,详细地描述为了达到项目的目标所需要进行的一些活动。
    There are some special activities called (),which are events that signify the accomplishment or completion of major deliverables during the project.
    在这些活动中有一些被称为里程碑( milestones)的特殊活动,这些活动中包含了标志项目的主要交付产品己经完成的事件。
    Most system development methodologies also provide (), whose purpose is to contain the various pieces of relevant information feasibility assessments, schedules, needs analysis, and so forth in a single place. So that they can be presented to project clients and other related parties.
    大多数系统开发方法都提供了基线计划( baseline plan),其目的是将一系列相关信息,如可行性评估、进度安排和需求分析等包含在一起,便于向项目的客户及相关团体展示。
    Several types of important network diagrams are used in project management. () was developed to make clear the interdependence between project tasks before those tasks are scheduled. () offers the advantage of clearly showing overlapping tasks.
    在项目管理中还用到了一些重要的网络图形。在对项目任务进行安排之前,可以使用PERT图清晰地展示这些任务之问的内在依赖关系。Gantt通常适用于现实具有并行关系的任务。

    问题1
    A Functional decomposition diagram
    B Work Breakdown Structure
    C Structure Chart
    D Organizational Structure
    问题2
    A feasibility checkpoints ;
    B phases
    C iterations
    D milestones
    问题3
    A baseline plan
    B project planning
    C statement of work
    D information system planning
    问题4
    A CPM
    B Network Diagram
    C PERT
    D Gantt chart
    问题5
    A CPM
    B Network Diagram
    C PERT
    D Gantt chart

    参考答案: BDACD