美文网首页
2019-05-31 每日一题

2019-05-31 每日一题

作者: 谁说咖啡不苦 | 来源:发表于2019-05-31 16:09 被阅读0次

    After a product is released for user acceptance testing, several defects are found. This
    results in the product being rejected by the customer,What should the project manager do next?
    A. Review the quality management plan using the defect analysis acceptance testing, and
    update if necessary.
    B. Advise the customer that the defects are within the product tolerance limits outlined in the
    quality management plan.
    C. Meet with the project team to review the product's requirement specifications.
    D. Hold a project team meeting to identify the problems, the time of the occurrence, and why it
    occurred.
    在一个产品发布用于用户验收测试后,发现了几个缺陷。这导致产品被客户拒收。项目
    经理下一步应该怎么做?
    A.审查质量管理计划时应用缺陷分析验收测试(标准),并在必要时更新。
    B.通知客户,缺陷在质量管理计划中概述的产品公差范围内。
    C.与项目团队开会审查产品的需求规范。
    D.召开项目团队会议,识别问题、发生的时间以及为什么会发生。
    答案:D
    解析:遇到问题首先分析问题、识别原因、然后解决问题。

    相关文章

      网友评论

          本文标题:2019-05-31 每日一题

          本文链接:https://www.haomeiwen.com/subject/vblgtctx.html