十号楼:十号楼东单元屋面机房层墙体模板拆模,六人
![](https://img.haomeiwen.com/i5232945/5028f04be87f14f9.jpg)
十号楼十一层砌体砌筑,完成百分之九十
![](https://img.haomeiwen.com/i5232945/0a1aa356a22c9dba.jpg)
九层构造柱浇筑混凝土。完成百分之六十,共计十二人
![](https://img.haomeiwen.com/i5232945/466256a492495f20.jpg)
![](https://img.haomeiwen.com/i5232945/4829d4cd94022bbf.jpg)
六层东单元粉刷打点
![](https://img.haomeiwen.com/i5232945/aed7f5e0fed6e720.jpg)
四至五层粉刷石膏施工。四层完成百分之九十,五层完成百分之二十,共计十人
![](https://img.haomeiwen.com/i5232945/91be1edda89bf4dc.jpg)
九号楼 : 九号楼屋面机房层拆模。主体材料清理
![](https://img.haomeiwen.com/i5232945/c0bd531b0508eb1a.jpg)
十一层止水台浇筑砼
![](https://img.haomeiwen.com/i5232945/4c30f364259abc12.jpg)
十层构造柱浇筑砼
![](https://img.haomeiwen.com/i5232945/8590e4f5e7b71136.jpg)
五层粉刷石膏打点,三至四层剪力墙及厨卫阳台喷浆
![](https://img.haomeiwen.com/i5232945/fbde2117908dd9a3.jpg)
一层砌体及二次结构完善
![](https://img.haomeiwen.com/i5232945/c2738ef56fcfd035.jpg)
六层七层过梁口找补
![](https://img.haomeiwen.com/i5232945/32878b9cc46cf79a.jpg)
3月17日工作计划:十号楼屋面机房层东单元拆模。西单元浇砼。十一层十二层砌体砌筑。九层构造柱浇筑砼。四至七层升降机处砌体砌筑。四至六层粉刷石膏施工。十一区车库顶板防水保护层施工。 九号楼。屋面机房层主体材料清理。电梯井上翻梁支模浇砼。十层外挑檐止水台支模。南侧阳台造型浇砼。七层砌体过梁口找补。三层粉刷冲筋施工,负一层砌体倒远,砌筑。