A company's director is concerned with project failure and hires a project manager to
determine where additional funding should be allocated to ensure success. For what activity
should the project manager recommend additional funding?
A. Warranty work
B.Rework
C.Testing
D. Scrap
公司董事担心项目失败,并聘用一名项目经理,以确定应分配额外的资金确保项目成功。
项目经理应建议对哪项活动分配额外资金?
A.保修工作
B.返工
C.测试
D.废料
答案:C
解析:本题点在于质量成本。预防胜于检查,测试属于质量成本中的一致性成本,其它三
项都属于非一致性成本。