An ongoing project is on schedule when a subject matter expert (SME) on the project's critical
path requests three days off, what should the project manager do?
A. Initiate a change request through performs integrated change control process.
B. Send a change request to the change control board (CCB) for approval.
C. Persuade the SME to work as planned; if unsuccessful, update the project management plan.
D. Identify this as a resource risk that is out of control, and update the risk register.
一个正在进行的项目正按进度计划进行,这时一名在项目关键路径上的主题专家(SME)
请求请三天假。项目经理应该怎么做?
A.通过执行整体变更控制过程提出变更请求。
B.向变更控制委员会(CCB)发送一份变更请求批准。
C.说服 SME 按计划工作:如果不成功,则更新项目管理计划。
D.将其识别为失控的资源风险,更新风险登记册。
答案:D。
解析:关键路径上的资源变更可能引起进度基准的变更,代表了不确定性,是风险。先查
看有无应急储备,如果实在没办法才提变更。
网友评论