美文网首页
2024-07-24 赶工计划及索赔跟进

2024-07-24 赶工计划及索赔跟进

作者: 木金木水火土的木 | 来源:发表于2024-07-23 22:48 被阅读0次

Subject: Proposed Steps to Settle the Onshore Contractor’s Claim No.1 and the Partial Acceleration Cost

References:

[if !supportLists]1. [endif]The officially submitted “Partial Acceleration Plan” dated XX/XX/202X;

[if !supportLists]2. [endif]The Employer’s acknowledgement of the “Partial Acceleration Plan”in Conzol dated XX/XX/202X;

[if !supportLists]3. [endif]The Onshore Contractor’s previous letters subjecting “Partial Acceleration Plan”;

[if !supportLists]4. [endif]The minutes of meetings involving “Partial Acceleration Plan”;

 

Attachment:

[if !supportLists]1. [endif]The comparison between the planned progress rate in the Baseline Schedule and the actual progress rate during the “Partial Acceleration”implementation;

[if !supportLists]2. [endif]The statistics of the Onshore Contractor’s monthly invested resources for conducting “Partial Acceleration Plan”.

Dear Sir,

Since November 2023, the Onshore Contractor has followed the Employer’s instruction, the Onshore Contractor has devoted himself in accelerating the progress rate in the last seven months to recover the progress lag resulting from all aspects. Hereby the “Partial Acceleration Plan”especially refers to the acceleration for the progress lag resulting from the Employer’s suspension under the event of “Employer’s Biodiversity Survey”.

As early as XX/XX/2023, the Parties via XXXXX,reached an agreement that the Onshore Contractor should prepare a detailed acceleration plan to recover the progress lag generated from all the Parties. Afterwards, the Onshore Contractor organized his personnel internally so as to draft a “Partial Acceleration Plan”. The aforesaid “Partial Acceleration Plan”was officially submitted on XX/XX/202X,which contains the acceleration measures in access road construction, WTG foundation construction, hardstanding construction. Please be kindly noted that such a “Partial Acceleration Plan”solely includes the costs for the Employer caused progress lag, the rest would be digested by the Onshore Contractor.

On XX/XX/202X,in Conzol system, after the Employer’s review, the status of the submitted “Partial Acceleration Plan”was “acknowledged by the Employer”. After that, there was no objection given by the Employer in conducting the “Partial Acceleration Plan”. As per the Onshore Contractor’s understanding, the methodology in the “Partial Acceleration Plan”had been approved, the only pending point was the costs.

Practically, the “Partial Acceleration Plan”was initiated by the Onshore Contractor as early as November 2023, which was even earlier than the officially submission date of the “Partial Acceleration Plan”(XX/XX/202X). At the time of the “Partial Acceleration Plan”submission, the cost was purely prospective cost, to accurately calculate the “Partial Acceleration Plan”actual cost, the monthly invested resources for conducting the “Partial Acceleration Plan” should be a scale-plate to evaluate the actual monthly acceleration cost. On the other hand, the effect of conducting the “Partial Acceleration Plan”can also be visualized by the comparison between the planned progress rate in the Baseline Schedule and the actual progress rate during the “Partial Acceleration”implementation.

To resolve the pending point of “Partial Acceleration Plan”cost, the Onshore Contractor hereby proposes the steps as follows:

Step-1

By submitting the comparison between the planned progress rate in the Baseline Schedule and the actual progress rate during the “Partial Acceleration”(See Attachment-1), the Employer can review and see the fruitful effect of conducting the “Partial Acceleration Plan”.   

Step-2

By submitting the statistics of the Onshore Contractor’s monthly invested resources for conducting “Partial Acceleration Plan”(See Attachment-2) and the actual duration of the acceleration, the Employer can review and verify the Onshore Contractor’s actual monthly invested resources so that later on the Parties are able to finalize the actual invested resources for conducting and actual duration the “Partial Acceleration Plan”.

Step-3

To finalize the above step-1 & step-2, necessary joint meetings are needed for such finalization.

Step-4

After the finalization of the “Partial Acceleration”effect and the actual invested resources, the Parties shall jointly evaluate and finalize the unit price of the sub-items of the “Partial Acceleration Plan”.

Step-5

The Onshore Contractor shall calculate and submit the actual cost for conducting the “Partial Acceleration Plan”based on the finalized actual invested resources for conducting and actual duration. The Employer shall review and determine the final cost.

Step-6

An settlement agreement shall be proposed after the Parties’confirmation of the final cost for the “Partial Acceleration”, which shall settle the dispute over the Onshore Contractor’s Claim No.1 and “Partial Acceleration Plan”.

May the Employer look deeply into the Onshore Contractor’s proposed steps to settle the Onshore Contractor’s Claim No.1 and the “Partial Acceleration Plan”.

Looking forward to the Employer’s positive reply.

相关文章

  • 4.28

    施工索赔的应用,索赔的起因与分类,索赔成立的条件,施工索赔的几个关键环节及注意事项; 索赔的起因与分类,索赔的起因...

  • PMP易混淆知识点

    6.5.2.6进度压缩:赶工VS快速跟进(P215): 赶工:增加资源,以最小的成本代价来压缩进度工期的一种技术(...

  • 物控计划,自我反省

    1、 和生产计划的衔接,随时做调整2、 物料申购计划的编制3、 采购订单的下单及跟进4、 物料交期的跟进(即不停工...

  • PMP-进度压缩:快速跟进和赶工区别和举例,附对比图收藏

    快速跟进VS赶工 原文链接:https://www.ffeeii.com/1636.html PMP中,很多同学对...

  • 周复盘2020.04.27-2020.05.03

    本周计划: 一.工作 1.上周方案跟进;√ 2.转介绍客户方案编制及跟进;√ 3.抽空写公号科普文章;❌ 这一周出...

  • 每日商务英语10句二十六

    二十六、索赔理由及依据 1、It was found by the inspection that there i...

  • 安踏跟进计划

    上午再继续拨打客户电话,下午约去肌肤恋和格莱德。再约两个客户周四去厦门。 针对大客户(特步、安踏、鸿星尔克等)跟进...

  • 201621周回顾

    一、情境综述 工作:重点围绕R项目及质量问题攻关开展工作。 素质:周计划实践进入第3阶段,加强跟进;日计划记录持续...

  • 三季度结束还有77天

    倒计时进行中,追赶工作计划,加油(ง •̀_•́)ง

  • 索赔的分类有哪些?2021-10-13

    索赔的分类有哪些?——(1)按索赔目的分:工期索赔和费用索赔。 (2)原因分:延期索赔、工程范围变更索赔、施工加速...

网友评论

      本文标题:2024-07-24 赶工计划及索赔跟进

      本文链接:https://www.haomeiwen.com/subject/lqeuhjtx.html